Parks Department
Providence Capital Infrastructure Investment PlanIn Providence, we have 120 parks totaling approximately 1,600 in total acreage; roughly 1/10th of all the land in Providence. The Parks Department not only maintains, repairs, and helps improve our parks, but helps activate these public spaces and engage residents and visitors with our city. This means creating parks and green spaces in every part of our community so that all of our visitors and residents can find a high-quality, well programmed, Providence park within a ten-minute walk.
PROJECT SUMMARY
Awarded Amount: $29,096,335.82
Amount Committed: $18,801,741.36
Remaining Balance: $10,294,594.46
Sewers
(Stormwater Consent Agreement)
CIP 1.4
Amount Funded: $1,500,000.00
Amount Committed: $1,449,374.63
Balance Remaining: $625.37
Mounted Command
CIP 2.38
Amount Funded: $666,000.00
Amount Committed: $661,050.00
Balance Remaining: $4,950.00
Construction 67%
India Point Park Improvements
CIP 3.01.01
Amount Funded: $567,000.00
Amount Committed: $16,702.33
Balance Remaining: $550,297.67
Design 70%
Manton Gateway Bike Park Install
CIP 3.11
Amount Funded: $474,797.85
Amount Committed: $474,797.85
Balance Remaining: $0
Project is complete
Manton Gateway
(Glenbridge Ave)
CIP 3.12
Amount Funded: $825,000.00
Amount Committed: $135,700.00
Balance Remaining: $689,300.00
Design 50%
Merino Park Improvements
CIP 3.15
Amount Funded: $119,236.78
Amount Committed: $119,236.78
Balance Remaining: $0
Project is complete
Mashapaug Boating Center – Building repairs/upgrades
CIP 3.20
Amount Funded: $50,000.00
Amount Committed: $49,800.00
Balance Remaining: $200
Project is complete
Ellery Street Park Improvements
CIP 3.35
Amount Funded: $147,100.00
Amount Committed: $147,100.00
Balance Remaining: $0
Project is complete
Bucklin Street Park Improvements
CIP 3.48
Amount Funded: $479,875.00
Amount Committed: $479,875.00
Balance Remaining: $0
Project is complete
Citywide Waterparks Improvements
CIP 3.64
Amount Funded: $ 300,000.00
Amount Committed: $300,000.00
Balance Remaining: $0
Project is complete
Arthur Ruby Lawrence Park Improvements
CIP 3.73
Amount Funded: $57,890.75
Amount Committed: $57,890.75
Balance Remaining: $0
Project is Complete
Amos Earley Park Improvements
CIP 3.75
Amount Funded: $86,760.00
Amount Committed: $86,760.00
Balance Remaining: $0
Project is complete
Ardoene Park Improvements
CIP 3.76
Amount Funded: $364,435.00
Amount Committed: $36,445.00
Balance Remaining: $327,990.00
Project is complete
Baxter Street Park Improvements
CIP 3.77
Amount Funded: $50,000.00
Amount Committed: $50,000.00
Balance Remaining: $0
Project is complete
Brassil Park Improvements
CIP 3.81
Amount Funded: $250,000.00
Amount Committed: $29,946.00
Balance Remaining: $220,054.00
Design 70%
Brown Street Park Improvements
CIP 3.82
Awarded Amount Funded: $160,925.78
Amount Committed: $160,925.78
Balance Remaining: $0
Project is complete
Clarence Street Park Improvements
CIP 3.86
Amount Funded: $35,000.00
Amount Committed: $35,000.00
Balance Remaining: $0
Project is complete
Columbus Sq. Improvements
CIP 3.88
Amount Funded $217,581.10
Amount Committed: $217,581.10
Balance Remaining: $0
Project is complete
Mt. Pleasant Field Improvements
CIP 3.90
Amount Funded: $209,000.00
Amount Committed: $209,000.00
Balance Remaining: $0
Construction 41%
Cranston Street Tot Lot Improvements
CIP 3.90
Amount Funded: $158,700.22
Amount Committed: $158,700.22
Balance Remaining: $0
Project is complete
Green School Yards
(Baxter Bailey Park)
CIP 3.90
Amount Funded: $999,923.03
Amount Committed: $999,923.03
Balance Remaining: $0
Project is complete
Ascham Street Park Improvements
CIP 3.90
Amount Funded: $200,500.00
Amount Committed: $200,500.00
Balance Remaining: $0
Construction 52%
Viscolosi Park Improvements
CIP 3.90
Amount Funded: $502,236.00
Amount Committed: $502,236.00
Balance Remaining: $0
Construction 20%
Collyer Park Improvements
CIP 3.90
Amount Funded: $129,853.00
Amount Committed: $129,853.00
Balance Remaining: $0
Construction 10%
Dexter Street Park Improvements
3.92
Amount Funded: $274,950.00
Amount Committed: $274,950.00
Balance Remaining: $0
Construction 90%
Donigian Park Improvements
3.93
Amount Funded: $115,170.00
Amount Committed: $115,170.00
Balance Remaining: $0
Project is complete
Fr. Lennon Park Improvements
3.95
Amount Funded: $162,614.75
Amount Committed: $162,614.75
Balance Remaining: $0
Project is complete
Gano Street Park Improvements
3.96
Amount Funded: $60,000.00
Amount Committed: $59,899.00
Balance Remaining: $101.00
Project is complete
General Street Park Improvements
3.97
Amount Funded: $210,226.31
Amount Committed: $6,120.00
Balance Remaining: $204,106.31
Gladys Potter Park Improvements
3.98
Amount Funded: $75,000.00
Amount Committed: $35,420.00
Balance Remaining: $39,580.00
Design 50%
Harriet and Sayles Park Improvements
3.100
Amount Funded: $2,028,802.00
Amount Committed: $2,028,802.00
Balance Remaining: $0
Construction 10%
Neutaconkanut Park Improvements
3.113
Amount Funded: $149,865.00
Amount Committed: $14,986.00
Balance Remaining: $134,879.00
Project is complete
Annie Morris Park Improvements
3.123
Amount Funded: $99,030.00
Amount Committed: $99,030.00
Balance Remaining: $0
Project is complete
Roger Williams Park
3.128
Amount Funded: $3,743,224.00
Amount Committed: $1,560.985.00
Balance Remaining: $2,182,239.00
41% complete
Morris Avenue Tot Lot Improvements
3.129
Amount Funded: $112,339.00
Amount Committed: $112,339.00
Balance Remaining: $0
Project is complete
Carriage House
3.131
Amount Funded: $4,333,818.21
Amount Committed: $4,333,818.21
Balance Remaining: $0
Project is complete
Roger Williams Zoo
3.132
Amount Funded: $2,000,000.00
Amount Committed: $350,000.00
Balance Remaining: $1,650,000.00
Jaqueline Clements Park Improvements
3.132
Amount Funded: $355,084.00
Amount Committed: $355,084.00
Construction 10%
J.T. Owens Park Improvements
3.132
Amount Funded: $332,000.00
Amount Committed: $332,000.00
Construction: 10%
Lippit Park Improvements
3.132
Amount Funded: $315,000.00
Amount Committed: $315,000.00
Locust Grove Cemetery lmp
3.132
Amount Funded: $175,483.04
Amount Committed: $175,483.04
Balance Remaining:
Construction: 70%
Paterson Park Improvements
3.132
Amount Funded: $150,000.00
Amount Committed: $150,000.00
Remaining Balance: $75,000.00
Design: 30%