Mt. Pleasant Fire Station Masonry Repairs

CIP 2.22.01

Financials

Awarded Amount: $75,000.00
Amount Committed: $99,643.00
Remaining Balance: $0

Mt Pleasant Fire Station Masonry Progress
Mt Pleasant Fire Station Masonry Progress

Hartford Avenue Fire Station Concrete Apron Repairs

CIP 2.24.01

Financials

Awarded Amount: $50,000.00
Amount Committed: $56,865.00
Remaining Balance: $0

Allens Avenue Fire Station Concrete Apron Repair

Reservoir Avenue Fire Station Concrete Apron Repairs

CIP 2.25.01

Financials

Awarded Amount: $50,000.00
Amount Committed: $56,089.00
Remaining Balance: $0

early design

Allens Avenue Fire Station Masonry Repairs

CIP 2.24.01

Financials

Awarded Amount: $75,000.00
Amount Committed: $92,345.00
Remaining Balance: $0

Allens Avenue Fire Station masonry repairs
Allens Avenue Fire Station

2.33 – Joslin Community Center

CIP 2.33

Financials:

Amount Funded: $1,700,000.00
Amount Committed: $1,359,481.33
Remaining Balance: $340,518.67

complete

Project notes:

The project consisted of renovating older spaces including new flooring, interior walls, and other improvements.
Architect: Torrado Architects
General Contractor: Martone Construction.

Project Status:

Construction completed: 11/22/2022

Unfinished walls and sprinklers

Finished interior space.

Renovated interior space.

Completed Second Floor Space

A Vincent Igliozzi Recreation Center- Exterior Sign and Renovations

Financials:

Awarded Amount: $288,963.00
Amount Committed: $288,963.00
Remaining Balance: $0

construction

Scope Work:

Create a new monumental freestanding sign with electronic message board at parking lot entrance to the Recreation center. Update building lettering and pool signage, including LED-lit letters above the main entrance. Install privacy fence slats in the existing chain link fence around pool. General Contractor services provided by Maron Construction Co, Inc.

Project Status:

Construction is substantially complete as of 2/10/2023.

Freestanding Message Board Sign

Building Entrance Lettering

Gym LetteringĀ 

Pool Sign & Privacy Fence SlatsĀ